Project Details
OPD provided engineering, design, procurement and construction of a grassroots, custom designed nominal 1.1 BSCFD rich gas cryogenic facility in West Texas. The scope included full design and EPC services for everything from concept to startup and from fence to fence.
Additional Details
- OPD modularized 3 x 330 MMSCFD cryo plants w/ refrigeration
- ~42 MBPD modularized stabilizers with truck loading and NGL blending
- Originally customized to be standard for this end-user
- Amine inlet treating (3 x 1500 GPM)
- Turbine-driven centrifugal residue compression
1.3 MILLION
man-hours from start to finish
Project Highlight:
“Our custom-designed modularization approach strategically reduced on-site labor and on-site material storage for this site.“
-Alex Hernandez, Construction Manager